Data centre site

Applied Digital Polaris Forge 1 (Ellendale)

Applied Digital’s Polaris Forge 1 AI Factory Campus in North Dakota, fully leased to CoreWeave and contracted for 400 MW of critical IT load at full build-out. It is partly operating: 250 MW was live by October 2026, while Building 3 (150 MW) was still being financed and built.

Location
Operator
Site
AI factory
Status
Operating 2 Oct 2026
Capacity
400 MW2026-10-02source ↗
Tenants
CoreWeave
Customers
EnterpriseWholesale
Domains
Data centresAI infrastructure

Ecosystem

  • No sourced relationships yet. A blank here is a fact about the evidence, not about the company.

Open Applied Digital Polaris Forge 1 (Ellendale) in the ecosystem →