Data centre site
Nebius Béthune (Azur Datacenter)
AI data centre being built in phases on the former Bridgestone tyre plant at Béthune, near Lille. Azur Datacenter pays for construction and leases the site wholesale to Nebius, which buys and runs the NVIDIA graphics processing units (GPUs); the full build-out is 240 megawatts (MW).
- Location
- Operator
- Site
- AI factory · Colocation
- Status
- Under construction 10 Jun 2026
- Capacity
- 240 MW2026-02-12source ↗
- Tenants
- Nebius
- Customers
- EnterpriseWholesale
- Domains
- Data centresAI infrastructure
Ecosystem
- No sourced relationships yet. A blank here is a fact about the evidence, not about the company.