CloudHQ QRO Campus, Querétaro

Wholesale hyperscale campus of six buildings on 52 hectares just west of Querétaro airport, powered from an on-site substation on the 400 kilovolt grid. CloudHQ’s campus page gives 360 megawatts (MW) of total critical IT load, ready for service within 2027; its chief operating officer spoke of up to 900 MW in September 2025.

Location
Operator
Site
Hyperscale
Status
Under construction 13 Oct 2026
Capacity
360 MW2026source ↗
Customers
EnterpriseWholesale
Domains
Data centres

Ecosystem

  • No sourced relationships yet. A blank here is a fact about the evidence, not about the company.