Stargate Abilene (Crusoe Abilene AI campus)
Eight-building AI data center campus developed by Crusoe on the Lancium Clean Campus and leased to Oracle for OpenAI’s first Stargate site. Crusoe gives the campus a total power capacity of 1.2 GW; the first two buildings (about 200 MW of IT) are live and the remaining six are due by the end of 2026.
- Location
- Operator
- Site
- AI factory · Hyperscale
- Status
- Operating 27 Mar 2026
- Capacity
- 1,200 MW2026-03-27source ↗
- Tenants
- Oracle · OpenAI
- Customers
- EnterpriseWholesale
- Domains
- Data centresAI infrastructure
Ecosystem
- No sourced relationships yet. A blank here is a fact about the evidence, not about the company.