Skip to main content
BSS/OSS Academy

Data centre site

Stargate Abilene (Crusoe Abilene AI campus)

Eight-building AI campus on the Lancium Clean Campus, developed by Crusoe, where Oracle Cloud Infrastructure (OCI) runs the compute for OpenAI’s first Stargate site. Crusoe gives 1.2 GW of total power capacity at completion; Oracle said in September 2026 that six of the eight buildings, 618 MW, had been delivered to the customer. OpenAI dropped a planned expansion here; Crusoe’s separate 900 MW campus next door now serves Microsoft and is not part of this site.

Location
Operator
Site
AI factory · Hyperscale
Status
Operating 27 Mar 2026
Capacity
1,200 MW2026-03-27source ↗
Tenants
OpenAI
Customers
EnterpriseWholesale
Domains
Data centresAI infrastructure

Ecosystem

  • No sourced relationships yet. A blank here is a fact about the evidence, not about the company.

Open Stargate Abilene (Crusoe Abilene AI campus) in the ecosystem →