Data centre site
Stargate Abilene (Crusoe Abilene AI campus)
Eight-building AI campus on the Lancium Clean Campus, developed by Crusoe, where Oracle Cloud Infrastructure (OCI) runs the compute for OpenAI’s first Stargate site. Crusoe gives 1.2 GW of total power capacity at completion; Oracle said in September 2026 that six of the eight buildings, 618 MW, had been delivered to the customer. OpenAI dropped a planned expansion here; Crusoe’s separate 900 MW campus next door now serves Microsoft and is not part of this site.
- Location
- Operator
- Site
- AI factory · Hyperscale
- Status
- Operating 27 Mar 2026
- Capacity
- 1,200 MW2026-03-27source ↗
- Tenants
- OpenAI
- Customers
- EnterpriseWholesale
- Domains
- Data centresAI infrastructure