Data centre site

Crusoe Abilene campus for Microsoft

Second Crusoe campus in Abilene, Texas, next to the Stargate Abilene site, built for Microsoft on Lancium-owned land. It has two buildings of 336 MW of critical IT load each and a 900 MW on-site power plant with battery storage.

Location
Operator
Site
AI factory · Hyperscale
Status
Under construction 27 Mar 2026
Capacity
900 MW2026-03-27source ↗
Tenants
Microsoft
Customers
EnterpriseWholesale
Domains
Data centresAI infrastructure

Ecosystem

  • No sourced relationships yet. A blank here is a fact about the evidence, not about the company.