Google’s first Wyoming data center, a USD 17 billion campus in Laramie County near Cheyenne announced on 5 November 2026, on the site Crusoe had developed with Tallgrass Energy as Project Jade (announced July 2025 at 1.8 GW, scalable to 10 GW). County filings reported by Cowboy State Daily describe a 716-acre, 2.7 GW campus in the Switchgrass Industrial Park built by a Google subsidiary, Jupiter Star Holdings, with completion planned by 2031; power comes from Tallgrass and Black Hills Energy gas generation plus a 702 MW fuel-cell development with carbon capture.
- Location
- Operator
- Site
- Hyperscale
- Status
- Planned 6 Nov 2026
- Capacity
- 2,700 MW2026-07-08source ↗
- Customers
- EnterpriseWholesale
- Domains
- Data centres
Ecosystem
- No sourced relationships yet. A blank here is a fact about the evidence, not about the company.