Meta Beaver Dam data center
Meta’s 30th data center, an AI-optimised campus of about 700,000 square feet in Alliant Energy’s Beaver Dam Commerce Park, Wisconsin, announced in November 2025 with an investment of more than USD 1 billion. Wisconsin regulators approved in May 2026 an Alliant Energy contract to supply the campus with 220 MW of power over a 10-year term; Alliant expects the site to come online in 2027.
- Location
- Operator
- Site
- Hyperscale · AI factory
- Status
- Under construction 14 Apr 2026
- Capacity
- 220 MW2026-05-08source ↗
- Customers
- EnterpriseWholesale
- Domains
- Data centresAI infrastructure
Ecosystem
- No sourced relationships yet. A blank here is a fact about the evidence, not about the company.