Meta New Albany Data Center (Prometheus)
Meta’s Prometheus AI supercluster at its New Albany, Ohio campus. Meta said in October 2026 that the first phase is complete and that the cluster is scaling towards about one million GPUs; 1 GW across several buildings, some of it leased from partners, is the completion target. Meta signed nuclear power deals with Vistra, TerraPower and Oklo in January 2026 partly to support it.
- Location
- Operator
- Site
- AI factory · Hyperscale
- Status
- Operating 19 Oct 2026
- Capacity
- 1,000 MW2026-01-09source ↗
- Customers
- EnterpriseWholesale
- Domains
- Data centresAI infrastructure
Ecosystem