Sber Balakovo data centre

Sber’s regional data centre in the Balakovo special economic zone (Saratov region), near the Balakovo nuclear plant: construction began in September 2021 on a 55,000 m² site of seven modules of 500 racks each, with design power reported at up to 82 MW. It was hit by drones on 14 October 2026 while still under construction; completion had been scheduled for 2027.

Location
Operator
Site
Hyperscale
Status
Under construction 14 Oct 2026
Capacity
82 MW2025-12-05source ↗