TeraWulf Lake Mariner (Barker)

TeraWulf campus on Lake Ontario in western New York, a bitcoin-mining site being converted for Fluidstack in three buildings (CB-3, CB-4 and CB-5). Fluidstack has contracted 360 MW of critical IT load, with Google guaranteeing about $3.2bn of its lease obligations.

Location
Operator
Site
AI factory · Colocation
Status
Under construction 19 Aug 2025
Capacity
360 MW2025-08-19source ↗
Tenants
Fluidstack
Customers
EnterpriseWholesale
Domains
Data centresAI infrastructure
Verified 7 Nov 2026 · DCD, DCD