Data centre site
Volcano Engine Taihang Computing Center (Datong)
ByteDance’s computing centre in the Guangling Economic and Technological Development Zone, Datong, Shanxi, built by its subsidiary Huoshan Cloud (Datong) Technology; phase 1 (construction from May 2023) and phase 2 are complete and in production, and a phase 2 expansion with four more data-hall buildings and its own 220 kV substation is planned for April 2026 to March 2028. No MW figure is published.
- Location
- Operator
- Site
- Hyperscale · AI factory
- Status
- Operating Mar 2026
- Capacity
- Not disclosed
- Customers
- EnterpriseWholesale
- Domains
- Data centresAI infrastructure
Ecosystem
- No sourced relationships yet. A blank here is a fact about the evidence, not about the company.
Open Volcano Engine Taihang Computing Center (Datong) in the ecosystem →