The Go-Live Date Nobody Will Move
Intermediate5 min+100 XP
Page 1 of 5
The Situation
Your role
BSS & OSS Project Manager
You are accountable for what actually goes live on the date, not only for the date itself.
A B2B managed connectivity product launches in six weeks, and three teams disagree about whether that is possible.
BSS says product configuration is almost complete. OSS says orchestration is behind. Network says activation depends on a change that has not been tested.
Sales has already committed the date to a named customer, and the Business Owner has said it cannot move.
“The date cannot move. Tell me what you need to hit it.”
BSS
Configuration nearly complete
Ready
OSS
Orchestration behind schedule
At risk
Network
Activation change untested
Blocked
6 weeks to launch — committed to a named customer